Warehouse
Using heavy duty epoxy and polyurethane based systems such as:
(e.g.,Luxafloor® Primer, Luxafloor® LGE, Luxafloor® PTX)

Warehouse Coating
01
Surface Preparation
-
Cleaning: Remove dust, oil, laitance, old coatings or contaminants via grinding, shot-blasting, or acid etching.
-
Moisture Check: Ensure concrete moisture content is below acceptable levels.
-
Crack Repair: Fill cracks or joints with an epoxy filler before priming.
02
Primer Application
-
Product: (e.g., Luxafloor® Primer)
-
Purpose: Enhances adhesion between concrete and top coatings.
-
Application: Roll evenly over surface; coverage approx.
6–8 m²/L.
-
Dry Time: Allow 4 hours before applying basecoat.
03
Basecoat (Mid Coat)
-
Product: (e.g., Luxafloor® LGE)
-
Properties:
-
High-solids epoxy with excellent resistance to impact, abrasion, and chemical exposure
-
Can be tinted to custom colors
-
Application: Apply 1–2 coats using roller or squeegee.
-
Dry Time: 4–6 hours between coats.
04
Topcoat (Optional for Gloss & UV)
-
Product: (e.g., Luxafloor® PTX)
-
Features:
-
UV-resistant polyurethane topcoat
-
Glossy or matte finish
-
Optional anti-slip aggregates for safety
-
Application: Roller or airless spray.
-
Dry Time: Walkable in 24 hours; full cure in 7 days.
05
Additional Tips
-
Safety Markings: Use high-contrast striping or color zoning for forklifts and walkways.
-
Anti-Slip: Add aggregates to topcoat where safety is a concern.
-
Temperature: Avoid application in temperatures under 10°C or above 35°C.